How to calculate
Subtract actual cost from earned value for cost variance and planned value for schedule variance. Divide earned value by each corresponding number for the performance indices.
Worked example
Use Budget at completion (USD) 100000 · Planned value to date (USD) 50000 · Earned value to date (USD) 40000 · Actual cost to date (USD) 45000. The result is -5000.00 USD.
Input and result notes
Use four project totals or enter task lines. If both are entered, task lines take precedence. All numbers should refer to the same status date.