How to calculate
Subtract each day’s completed points from the previous balance. The ideal line starts at total planned points and reaches zero at the end of the sprint.
Worked example
Use Working days in sprint 10 · Starting story points 35 · Points completed on each elapsed day 3, 4, 2, 3, 3. The result is 20 points.
Input and result notes
Enter zero on a day with no completed items. A negative entry adds scope and raises the remaining balance.