How to calculate
Add the optimistic duration, four times the most likely duration and the pessimistic duration. Divide by six for the PERT weighted duration. Divide the high to low spread by six for the conventional standard deviation estimate, then square it for variance. The triangular estimate gives each input equal weight.
Worked example
Use Three point estimate method PERT weighted estimate · Optimistic duration 4 · Most likely duration 7 · Pessimistic duration 16 · Duration unit days. The result is ≈ 8 days.
Input and result notes
Use optimistic ≤ most likely ≤ pessimistic. Review uncertain project schedules by considering task relationships and correlated risks.
PMI project estimating practice standard overview